Observing the attached PDM diagram, how many days would it take to execute the project beginning to end? (Assume 1 week =5 days)
The total number of days to execute the project from beginning to end is 98 days.
The total number of days to execute the project from beginning to end is 46 days.
None of these
The total number of days to execute the project from beginning to end is 53 days.
The total number of days to execute the project from beginning to end is 60 days.
The correct answer is 70 days to complete project beginning to end, critical path is items 1,2,3,4,5,8,9, 10, & 11 and a week is equivalent to 5 days. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.