The total number of weeks to execute the project from beginning to end is 11 weeks and 7 days.
None of these
The total number of weeks to execute the project from beginning to end is 12 weeks.
The total number of weeks to execute the project from beginning to end is 10 weeks.
The total number of weeks to execute the project from beginning to end is 10 weeks and 2 days.
The correct answer is if item 11 is increased from 1 to 2 days, it still is not on critical path so will still be 12weeks to complete project beginning to end, critical path is items 1,2,3,5,8,12,13,14 and a week is equivalent to 7 days. (PMBOK 2013 Rev 5th Edition, pgs 177-180).
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.