True or False: Estimate Activities Resources is another process that is progressively elaborated as more detail about a project is developed.
True
False
True. One more process that is progressively elaborated as more detail about a project is developed is "Estimate Activity Resources." For example: In the beginning of a project, the team may know the type of skills that are needed. As the project progresses, the team is able to determine the skill level and number of workers they have and will continue to need.