A Solar Installation Company has a project to install solar arrays on a new office building downtown. The following are details, which are required to complete the project, what is duration of project once contract is provided to building owner. [Note 1 week=5 days] 1. Sales Person to contact building office owner -1 day. 2. Provide Contract for Office Building Owner -1 week 3. Design Solar Array Layout -2 weeks 4. Design Approval by Customer -3 days 5. Fabricate Solar Array and Framing _6 weeks 6. Obtain Permits - 1week 7. Schedule construction _ 3 days 8. Deliver Materials to site _ 2 days 9. Install framing, electric, and solar arrays _ 1 week 10. Acceptance of Installation by Office Building Owner -1Day

None of these

12 weeks

11 weeks

10 weeks

15 weeks

Explanation

T42-Estimate Resource Activities ITTOs

Video Training

Train with Skillset and pass your certification exam. Faster. Guaranteed.

Directory

Skillset helps you pass your certification exam.

Contributions and Interactions
Practice Questions

Study thousands of practice questions that organized by skills and ranked by difficulty.

Contributions and Interactions
Personalized Training

Create a tailored training plan based on the knowledge you already possess.

Training Video Selector
Exam Readiness

Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.

Get A Free Skillset Account