What should be validated initially prior to modifying a project by adding resources to tasks with time constraints?
The length of the remaining tasks
The critical path for the project
The personnel assigned to other tasks
The project budget
Since adding resources may change the route of the critical path, the critical path must be reevaluated to ensure that additional resources will in fact shorten the project duration. Given that there may be slack time available on some of the other tasks not on the critical path, factors such as the project budget, the length of other tasks and the personnel assigned to them may or may not be affected.