What types of relationships exist between project phases?
Progressive, Projectized, Incentivized
None of these
Sequential, Overlapping, Iterative
Lag, Lead, Critical
Project phases can have the following types of relationships: sequential, overlapping, or iterative. In sequential relationships, a new phase can only start once the previous phase is complete. In an overlapping relationship, a phase may start prior to the completion of the previous one. In an iterative relationship, only one phase is planned at a time.