Which of the following explains the need for a contingency plan while completing a risk management plan?
When unknown risks cannot be managed proactively
When known risks occur and have a larger than anticipated impact on the project
When unknown risks have been identified in the risk management plan
When known risks can be managed proactively
Contingency plans deal with unknown risks, not known risks HOW DOES THIS MAKE SENSE WITH THIS ANSWER