You just took over project management of a project for a project manager who has left the company. The project is getting ready to enter the Direct and Manage Project Work process. Which of the listed is not an input to this process?
Project management plan
Approved change requests
Project charter
Organizational process assets
The Project charter is not an input to the Direct and Manage Project Work process, it is an input to the Develop Project Management Plan process. The four inputs to the Direct and Manage Project Work process are the project management plan, approved change requests, enterprise environmental factors, and organizational process assets. (PMBOK 5th Edition pg 79)
Train with Skillset and pass your certification exam. Faster. Guaranteed.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.