A two year task has 200 work packages, and a $20,000 budget. After a year, 100 packages are ready, and $10,000 has been spent. Which of the following applies?
The task needs 50 work packages to be finished in 3 months
The task is on timetable and budget
The task needs 50 work packages to be finished in 6 months
Not enough data is available
(Awful Question! Surely it's on budget & time)