Ben has 3 projects, with the following conditions: Project 1 _ CPI=.9 & SPI =.9 is inClosing Phase of Project, Project 2- CPI=1.1 & SPI=.9 is in Execution phase of project, Project 3 _ CPI= 1.0 & SPI=.95 is in Planning phase of project. Which of his projects will he most likely be able to change the outcome so that both CPI and SPI are on or under budget and on or ahead schedule?
Project 1
Project 2 and 3
Project 2
Project 1 and 3
Let's first look at the definition of Schedule Performance Index and Cost Performance Index; A value >1 shows ahead of planned schedule and under planned cost, a value<1.0 is behind planned schedule and over budgeted cost, and a value=1.0 is on planned schedule and on planned cost. Both Project 2 and 3 meet the critieria for being able to modify the outcome
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.