Butch has 4 projects, with the following conditions: Project 1 _ CPI=.7 & SPI =.9, Project 2- CPI=1.0 & SPI=.7, Project 3 _ CPI= 1.0 & SPI=1.1, Project 4- CPI=.6 & SPI=1.1. Which of his projects are behind on planned cost and schedule?
Project 2
Project 4
Project 1
Project 3
Let's first look at the definition of Schedule Performance Index and Cost Performance Index; A value >1 shows ahead of planned schedule and under planned cost, a value<1.0 is behind planned schedule and over budgeted cost, and a value=1.0 is on planned schedule and on planned cost. Based on these definitions, Project 1 is the only project that meets the criteria.