Skillset can help you prepare! Sign up for your free Skillset account and take the first steps towards your certification.
Jeremiah has 4 projects, with the following conditions: Project 1 _ CPI=.8 & SPI =.9, Project 2- CPI=1.1 & SPI=.8, Project 3 _ CPI= 1.0 & SPI=1.0, and Project 4- CPI=.6 & SPI=1.2 Which of his projects does he need to ask for support to get back on track at this point in time?
Project 2,3 & 4
None of the Projects
Project 1,3, & 4
Project 1, 2 & 4
Let's first look at the definition of Schedule Performance Index and Cost Performance Index; A value >1 shows ahead of planned schedule and under planned cost, a value<1.0 is behind planned schedule and over budgeted cost, and a value=1.0 is on planned schedule and on planned cost. Projects 1,2, and 4 all need support at this time they are behind schedule.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.