Multiple documents originating from initiation, execution or control processes are used for supporting inputs for the Control Stakeholder Engagement process. This is called __________.
Project documents
Lessons learned documentation
Work performance data
Issue log
This is a standard definition used in the PMBOK Guide under the Control Stakeholder Engagement process in Project Stakeholder Management.