Nick has 3 projects, with the following conditions: Project 1 _ CPI=1.28 & SPI =1.19 is in Execution Phase of Project, Project 2- CPI=1.05 & SPI=1.15 is in Execution phase of project, Project 3 _ CPI= 1.05 & SPI=1.1 is in Execution phase of project. From the CPI and SPI parameters alone are any of these projects at risk?
Project 1
None
Project 3
Project 2
Let's first look at the definition of Schedule Performance Index and Cost Performance Index; A value >1 shows ahead of planned schedule and under planned cost, a value<1.0 is behind planned schedule and over budgeted cost, and a value=1.0 is on planned schedule and on planned cost. All 3 projects are under budget/ahead of plan. In reality, CPI/SPI is only a snapshot in time of project status, so a more accurate answer is actually indeterminant as there is not enough information on their go forward status.
Study thousands of practice questions that organized by skills and ranked by difficulty.
Create a tailored training plan based on the knowledge you already possess.
Know when you’re ready for the high-stakes exam. Have the confidence that you will pass on your first attempt.